Extra Over???

  [复制链接]
发表于 17-10-2010 06:51 PM | 显示全部楼层
case 1

BQ item

1.1)Excavation in earth > m3 > 1000(Qty) > 3.50(Rate)
1.2)Extra over  ...
alias9 发表于 23-9-2009 06:07 PM



thanks for sharing.... i learn something. 谢谢。
回复

使用道具 举报


ADVERTISEMENT

发表于 29-10-2010 04:34 PM | 显示全部楼层
幸好有你们在,我才能把还了给教授的东西给抢回来!
回复

使用道具 举报

发表于 31-10-2010 06:54 PM | 显示全部楼层
回复 22# iceloo

等你请喝茶~~~
回复

使用道具 举报

发表于 31-1-2015 11:10 AM | 显示全部楼层
请问 Extra over 和 Extra over for 有何分别?
回复

使用道具 举报

发表于 1-2-2015 03:18 PM | 显示全部楼层
shaoching 发表于 18-9-2009 01:02 PM
我懂的是
好像你的铁一支12m,但你只用到11m,所以1m是extra over 咯。
但那1m你也是要给钱的,所以如果你 ...

Brother, this is wastage lah not extra over lah o.k, this wastage shall put under your unit rate lah

回复

使用道具 举报

发表于 1-2-2015 03:31 PM | 显示全部楼层
extra for and extra over for is same, "extra over for" got many item can put in, but some QS Consultant not do that
because they dun know, below is same item we can calculate as "Extra over for " :-

1) Railing, usually we price railing in meter run, but we still can claim or prepare the BQ with "Extra over for "
  - Bend
  - End Cap

2) Floor Tiles also have extra over for :-
  - Extra over for floor trap
  - RWDP opening
  - Scupper drain

3) Ceiling also have "Extra over for" :-
  - Opening Access

many many item we can put into BQ with "Extra over for" but sad is Our QS Consultant (All Malaysia) not included because of no standard ppl prepare BQ.
So as a Contractor they shall included into their unit rate. during Tender Interview Consultant will going to said your unit rate too high and market are only RM xxx

This is Malaysia Standard, in KL, almost IR is for ALL, he can be a Architect & QS, This IR fee very high, he prepare all documents, tender drawings, tender interview, tender reports and .......


回复

使用道具 举报

Follow Us
发表于 7-2-2015 03:58 PM 来自手机 | 显示全部楼层
适当的了解和应用“Extra Over"这个字眼,因为这会大大影响你的pricing。
例子1 - soil excavation 1000m3 at RM10/m3. 当挖的过程很大可能会遇到有hard rock,所以我们会有extra over for rock excavation at 100m3(e.g. 10%), 这100m3其实是part of your 1000m3, 所以你已经打了价钱在你的soil excavation at RM10/m3里,如果你的rock excavation是RM30/m3的话,那么你的extra over for rock excavation就是 RM30/m3 减RM10/m3 = RM20/m3。不放extra over的话就会出现double accounting了。
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 注册

本版积分规则

 

ADVERTISEMENT



ADVERTISEMENT



ADVERTISEMENT

ADVERTISEMENT


版权所有 © 1996-2023 Cari Internet Sdn Bhd (483575-W)|IPSERVERONE 提供云主机|广告刊登|关于我们|私隐权|免控|投诉|联络|脸书|佳礼资讯网

GMT+8, 2-12-2024 08:36 PM , Processed in 0.097756 second(s), 18 queries , Gzip On.

Powered by Discuz! X3.4

Copyright © 2001-2021, Tencent Cloud.

快速回复 返回顶部 返回列表