SMRT acknowledges lapse in procedure before fatal accident
Before the team is allowed to step back on to the trackway, the following procedure must be carried out: The team must coordinate with the Signal unit at the station for oncoming trains to be brought to a stop and to ensure that no trains enter the affected sector. Our records do not show that this procedure took place.
Pasir Ris MRT station is a terminal station with two platforms. Trains arriving at Pasir Ris can berth at either platform. Trains can cross from one track to the other as they approach the station. In this accident, the train moving in automatic mode was routed to Platform 2. When the train captain saw staff on the track, he immediately applied emergency brakes but was unable to prevent the accident.